Building a new home in Pebble Beach: the path from lot or teardown to move-in
A new house in the Del Monte Forest needs two sets of approvals, one private and one public, and it starts with water. Here is the order things usually happen in, from the Pebble Beach Company’s Architectural Review Board guidelines, Monterey County and the state.
By Jonathan Balog, Broker Associate, Compass · Carmel-by-the-Sea · Facts checked Nov 22, 2026
The short version: Every new house in Pebble Beach needs approval from the Del Monte Forest Architectural Review Board (ARB) and from Monterey County. The ARB generally responds within 30 days of a correctly completed submittal, encourages preliminary ARB approval before you apply to the county, and its approval is revoked after one year unless work has begun or it grants an extension. The county requires Design Approval for parcels in the Del Monte Forest Land Use Plan, plus a coastal development permit or a coastal exemption and a building permit. Because all of the Del Monte Forest is seaward of the first through public road, the county’s coastal permit approvals there are appealable to the Coastal Commission, which has a 10-working-day appeal period. Work hours are Monday to Saturday, 8 a.m. to 6 p.m.
ARB response
Generally, after a correctly completed submittal.
ARB approval
Revoked after a year unless work has begun.
Coastal appeal
Working days, once the Commission gets the county notice.
Work hours
Monday to Saturday; none Sundays or federal holidays.
Two ways to a new house: a lot or a teardown
The approvals are similar. The first question is different.
Buying a lot
On a lot, water comes first. Whether the lot has a water entitlement, and how it can be used, decides whether a house can get a meter.
My Pebble Beach lots guide covers water entitlement, habitat, slope and coverage limits in detail, so they are not repeated here.
- Water first
- Site studies
Buying a teardown
A teardown already has a water meter and fixtures on record, but any increase in water use needs an MPWMD water permit, which is what lets an applicant get a building permit and intensify use of a meter.
Trees, slopes and setbacks on the existing site still shape what can replace the house.
- Existing meter
- Water permit
Water: Pebble Beach entitlements and Pure Water Monterey
Water is the first question for a new house in the Forest.
Pebble Beach Company entitlements
MPWMD Rule 23.5 covers water entitlements held by the Pebble Beach Company and others for listed Benefited Properties. A water use permit under the rule is a vested property interest, is not reduced by a water moratorium, and lets the owner get Cal Am water service, including a new meter, notwithstanding a moratorium on new connections, once fees are paid and a water permit application is complete.
Where it comes from
The entitlement is tied to the CAWD/PBCSD Reclamation Project, a partnership of the Pebble Beach Community Services District, the Carmel Area Wastewater District, MPWMD and the Pebble Beach Company. PBCSD says the project’s recycled water irrigates golf courses, athletic fields and other recreation areas in Pebble Beach, and has replaced an average of over 800 acre-feet of potable water a year.
Pure Water Monterey
MPWMD says the Pure Water Monterey expansion was completed in October 2025 and now supplies 60% of the Peninsula’s drinking water. Allocations from it go only to projects with an existing water meter while the State Water Board’s meter moratorium on Cal Am stands.
The county’s share
Pebble Beach is unincorporated, so its allocation is the county’s. The Board of Supervisors approved a Water Allocation Policy on June 10, 2026, and the county says it is still preparing the forms and FAQs for requesting water.
What it means for building new
A lot with water under a Rule 23.5 permit can get a new meter now, once the other approvals are in place. A lot without water on record needs a new meter. Unless it is a Benefited Property that can obtain Pebble Beach Company entitlement water, it waits on the State Water Board. No decision on lifting the moratorium was posted on the Board’s Cal Am page as of November 22, 2026. See the lots guide for how to check a lot.
MPWMD Rule 23.5 (PDF) ↗PBCSD: recycled water ↗MPWMD: Pure Water Monterey ↗MPWMD 2025 annual report (PDF) ↗County water allocation policy ↗State Water Board: Cal Am order ↗
The approvals, in the order they usually happen
The ARB is private review under your deed. The county permits are public. You need both.
1. Water and title
Confirm water for the house you want, and read the deed for restrictions. Some properties are restricted by deed to single-story homes.
2. Site reports
The Del Monte Forest Land Use Plan calls for technical reports, such as soils, geologic, geotechnical and fire hazard reports, prepared by qualified professionals. Geologic and geotechnical reports are required for unstable areas and all blufftop development.
3. ARB preliminary review
The ARB prefers preliminary plans for extensive or complex proposals and encourages applicants to get preliminary ARB approval before applying to the county. As a courtesy, adjacent owners may be notified of a major application such as a new residence.
4. County Design Approval
Monterey County requires Design Approval for all parcels in the Del Monte Forest Land Use Plan. Simple projects may be approved by staff; more complex ones go to a neighborhood Land Use Advisory Committee and the Zoning Administrator.
5. Coastal permit and appeals
A county coastal development permit, or a coastal exemption, is needed in the coastal zone. An approved county application is not final until ten days pass for a local appeal. Because all of the Del Monte Forest is seaward of the first through public road, county CDP approvals there are also appealable to the Coastal Commission, which allows 10 working days after it receives a complete notice of the county’s final action.
6. Building and utility permits
The county issues building permits to a property owner for work on a single-family home, or to a licensed contractor. The Pebble Beach Community Services District runs its own sewer permit process.
7. Keep approvals alive
ARB approval is revoked after one year unless work has begun or the ARB grants an extension. A county coastal permit for buildings generally expires two years after it is granted unless construction has begun, if no other date is set.
ARB guidelines (PDF) ↗County permit types ↗Del Monte Forest LUP (PDF) ↗Coastal Commission appeals (PDF) ↗PBCSD sewer permits ↗
More on the county side: Monterey County building permits and coastal development permits.
The design limits that shape a new house
Headline numbers from the ARB guidelines. The full rule set is in my building and remodeling in Pebble Beach guide.
Height
County zoning applies. Depending on the site and lot size, the main structure may not exceed 30 feet; in certain subdivisions 27 feet; and some properties are deed-restricted to single story.
Accessory buildings and ADUs
Accessory structures may not exceed 15 feet and ADUs 16 feet. See ADU rules.
Fences and walls
Fences, freestanding walls and retaining walls may not exceed six feet, measured from existing grade.
What the ARB does not review
The ARB reviews design, appearance and environmental fit. Its guidelines say it takes no responsibility for structural or mechanical soundness, which is for your design team and the county.
Trees, faults and the forest setting
The site often decides where the house can sit.
Native trees
The Del Monte Forest Property Owners say a permit is required for all removals of native tree species, and homes in the coastal zone may also need a Monterey County permit. The county handles up to three trees administratively; more need a coastal development permit.
Fault setbacks
The Land Use Plan requires occupied structures to be set back at least 50 feet from an active or potentially active fault, as determined by geologic investigation. It names the Cypress Point fault and minor faulting in the Pescadero Canyon area as likely the most significant local seismic hazards. See earthquake risk in Carmel and Pebble Beach.
Grading
The plan asks that development follow site topography and keep grading to a minimum, with disturbed areas replanted with native species. The county requires a grading permit at 100 cubic yards of cut and fill, and in some other cases.
During construction: inspections, gates and hours
The ARB stays involved until the end.
ARB inspections
The guidelines list a tree removal and building stakeout inspection first, a setback inspection when foundation forms are in place before concrete is poured, and a final inspection before occupancy. Staff inspections can generally be arranged 48 hours ahead.
Work hours
Monday to Saturday, 8 a.m. to 6 p.m., with no work on Sundays and federal holidays. The DMFPO suggests putting the hours in contractor contract language.
Vehicles and gates
Construction vehicles must be kept on the permitted property and may not block traffic. Contractors are not admitted at night except for emergency repairs. See the Pebble Beach gate pass guide.
Hiring the team
For license, insurance, contract and payment checks, see how to hire a builder in Carmel and Pebble Beach.
Energy code and buyer protections
For a house you build, and for one you buy from a builder.
2025 Energy Code
Permit applications made on or after January 1, 2026 must comply with the 2025 Energy Code, which expands heat pumps in new homes and strengthens ventilation standards.
Buying a newly built house
California Civil Code Title 7 applies to original construction intended to be sold as an individual dwelling unit, with a general 10-year limit after substantial completion under Section 941. Ask an attorney how it applies.
Energy Commission: 2025 code ↗Civil Code 896 ↗Civil Code 941 ↗
Related guides
Other guides on this site that pair with this one.
- Buying a home in Carmel
- Buying a home in Carmel-by-the-Sea
- Buying a home in Pebble Beach
- Best real estate agent in Carmel
- Choosing an agent in Carmel-by-the-Sea
- Best real estate agent in Pebble Beach
- Pebble Beach lots for sale
- Building or remodeling in Pebble Beach
- Pebble Beach tree permits
- Pebble Beach gate pass
- Pebble Beach oceanfront homes
- Coastal development permits
- Monterey County building permits
- New construction in Carmel-by-the-Sea
- How to hire a builder
- Earthquake risk
- Pebble Beach market stats
Planning to build in the Forest? Start with water and the deed.
Before you commit to a lot or a teardown, I can help you gather the water, title and permit history and line up the questions for the ARB, the county and your design team.
Pebble Beach homesLots guideMarket stats
Questions about a specific property?
Call or text 831-747-0310, or book a 30-minute call. I am a Broker Associate with Compass, DRE 01980970.
Before you rely on this
- This is general information, not legal, design or construction advice. Confirm a specific project with the Del Monte Forest ARB, (831) 625-8455, and Monterey County Housing and Community Development.
- The ARB guidelines quoted are the version effective April 1, 2022 posted by the DMFPO; ask the ARB for the current version and fee schedule.
- Facts checked Nov 22, 2026 against the ARB guidelines, the DMFPO, Monterey County, the Del Monte Forest Land Use Plan, MPWMD, PBCSD, the Coastal Commission and the Energy Commission.
Building a new home in Pebble Beach: quick questions
Is water available to build a new home in Pebble Beach?
It depends on the lot. A lot with a water use permit under MPWMD Rule 23.5 can get a new meter despite the moratorium. Pure Water Monterey allocations go only to properties with an existing meter until the State Water Board acts on lifting the moratorium.
What approvals do I need to build a new house in Pebble Beach?
Del Monte Forest Architectural Review Board approval, plus Monterey County Design Approval, a coastal development permit or coastal exemption, and a building permit. You also need water for the house, an MPWMD water permit and a PBCSD sewer permit.
How long does ARB review take for a new home?
The ARB says it will generally respond within 30 days of a correctly completed submittal, but may take longer for complex or incomplete applications.
Should I go to the ARB or the county first?
The ARB guidelines encourage applicants to get preliminary ARB approval before applying to the county for design approval and a building permit.
Can a Pebble Beach coastal permit be appealed to the Coastal Commission?
Yes. The Del Monte Forest Land Use Plan says all of the Forest is seaward of the first through public road, so all county coastal permit approvals there are appealable. The Commission’s appeal period is 10 working days after it receives a complete notice of the county’s final action.
How tall can a new house be in Pebble Beach?
Depending on the site and lot size, up to 30 feet, or 27 feet in certain subdivisions, and some lots are deed-restricted to single story.
Do I need a permit to remove trees to build?
Yes, for native species. The DMFPO says a permit is required for all native tree removals, and coastal-zone homes may also need a county permit.
What are construction hours in Pebble Beach?
Monday to Saturday, 8 a.m. to 6 p.m., with no work on Sundays or federal holidays.
Get The Balog Report.
Peninsula market notes, Carmel-by-the-Sea and Pebble Beach listings worth a look, and the practical local tips I share with clients between showings.
Want a sample? Read the latest issue. Planning a move? Get in touch.
The next issue of The Balog Report will land in your inbox. Can’t wait? Read the latest issue.