Carmel Highlands coastal permits: what it takes to build or remodel
Carmel Highlands is unincorporated Monterey County, inside the California Coastal Zone, and covered by the County’s Carmel Area Land Use Plan. That means most new houses and many remodels need coastal permits on top of a building permit. Here is how the rules fit together, from the County code and the Coastal Commission.
By Jonathan Balog, Broker Associate, Compass · Carmel-by-the-Sea · Facts checked Nov 17, 2026
The short version: Carmel Highlands is in the Coastal Zone and covered by Part 4 of Monterey County’s Local Coastal Program, the Carmel Area Land Use Plan and its Coastal Implementation Plan. The County issues Coastal Development Permits there, and some decisions can be appealed to the California Coastal Commission within ten working days. Maintenance and additions to an existing house are often exempt, but not within 50 feet of a coastal bluff edge, not for wells or septic systems, and not, close to the sea or in scenic road corridors, for additions of 10% or more of floor area or a new story. The Carmel Area plan says new development in Carmel Highlands must be carefully sited and designed to minimize visibility, and the County also requires Design Approval in the Carmel Area.
Carmel Area plan
Of the County’s Local Coastal Program.
Bluff edge
Work within 50 feet of a bluff edge needs a permit.
Floor area trigger
Near the sea or a scenic road corridor.
Appeal window
Working days to appeal to the Coastal Commission.
The layers of rules in Carmel Highlands
Three sets of rules can apply to the same project.
The Coastal Act and Commission
The California Coastal Commission certified the Carmel Area Land Use Plan in 1983, and the County’s implementing zoning was certified in 1987. Once a local coastal program is certified, the local government issues most Coastal Development Permits, while the Commission keeps original jurisdiction in some areas and hears appeals.
The Carmel Area Land Use Plan
The County lists the Carmel Area Land Use Plan, its maps, and the Carmel Coastal Implementation Plan as Part 4 of its coastal plans, along with an appendix mapping the area of appeal to the Coastal Commission.
County permits
Monterey County Housing and Community Development handles coastal permits, Design Approval and building permits. Its permit types page says the Carmel Area is one of the plan areas where Design Approval applies.
A local advisory committee
The Carmel Highlands Land Use Advisory Committee reviews project referrals from the County and sends its recommendation to the planner before a hearing.
Monterey County: land use plans ↗California Coastal Commission: CDPs ↗
When a house project needs a Coastal Development Permit
Monterey County Code section 20.70.120 exempts maintenance, alterations and additions to an existing single-family home, then lists the exceptions that still need a permit.
Near the bluff or beach
Improvements on a beach or wetland, seaward of the mean high tide line, or within 50 feet of a coastal bluff edge need a permit. So does significant landform alteration, including removing vegetation, within 50 feet of a bluff edge.
Close to the sea, or in a scenic road corridor
Between the sea and the first public road, within 300 feet of the beach or mean high tide, or in a scenic road corridor, a permit is needed for an addition of 10% or more of internal floor area, a new story or loft, a detached garage over 1,000 square feet, a fence over 6 feet, shoreline protection, or a satellite dish.
Wells, septic and water-heavy features
Building or expanding a water well or septic system needs a permit. In areas with a critically short water supply, so do swimming pools and new or extended landscape irrigation.
Earlier permit conditions
If an earlier County or Coastal Commission permit for the property said future additions need a permit, they do. Read the permit history before you plan.
Even when a project is exempt, the code says other permits are unaffected, so you may still need Design Approval and a building permit.
Viewshed, ridgelines and steep slopes
The rules that most often shape a Highlands house.
Minimize visibility
Carmel Area Land Use Plan policy 2.2.3.3, quoted by the Coastal Commission, says new development on slopes and ridges in the public viewshed must be sited in existing forested areas or where topography hides it from major public viewpoints, not on non-forested slopes or silhouetted ridgelines, and that new development in Carmel Highlands and Carmel Meadows must be carefully sited and designed to minimize visibility.
Slopes over 30%
The Coastal Commission notes that the County’s implementation plan requires, as a condition of approval, that portions of a property with slopes greater than 30% be placed in a scenic easement. Building on those slopes takes its own Coastal Development Permit.
Habitat
Plan policies keep development out of environmentally sensitive habitat and require new development next to it to be compatible with protecting it. Biology reports are common in the Highlands.
A real example
A 2024 County referral for a new house on Crest Road in the Highlands combined a Coastal Administrative Permit and Design Approval for the house with separate Coastal Development Permits for development on slopes over 30% and within 750 feet of known archaeological resources.
Coastal Commission staff report on Carmel Highlands (PDF) ↗County file: Crest Road referral (PDF) ↗
How the process usually runs
From the County code, in plain terms. Timelines depend on the project.
1. Check the parcel
Find out whether the lot is in the appeal area, near a bluff, on steep slopes, near habitat or archaeological sites, or under earlier permit conditions. A survey and the permit history help.
2. Design and reports
Plans go through County planning, with Design Approval in the Carmel Area, and often geology, biology, archaeology and tree reports. The Carmel Highlands Land Use Advisory Committee may review the project.
3. Decision and appeals
After a County decision on an appealable Coastal Development Permit, the permit takes effect only after the ten working day appeal period to the Coastal Commission ends, or after any appeal is resolved.
4. Use it or lose it
A permit for buildings stays valid if construction starts within two years, unless it says otherwise. The planning director can extend a permit by two years on a written request made at least 30 days before it expires.
If any part of a lot is in a mapped flood zone, for example near a creek, get an elevation certificate before you design or buy. For County building permits generally, see my Monterey County building permits guide, and for the statewide picture, coastal development permits in Monterey County.
What this means when you buy in Carmel Highlands
Permits are part of the price of a Highlands property.
Before you write an offer
Ask for the permit history, any recorded scenic or conservation easements, and earlier permit conditions. They tell you what you can add later.
Plan for time
A remodel that triggers a Coastal Development Permit, Design Approval and reports takes longer than a simple building permit. Talk to an architect who works in the Carmel Area before you count on an addition.
Lots and teardowns
On a vacant lot or a teardown, slope, visibility and habitat can limit where and how big you build. Get a feasibility review early.
Experience matters
I have worked on many significant Carmel Highlands sales, and these permit questions come up in nearly every one. See Carmel Highlands homes for sale and choosing a Carmel Highlands agent.
Related guides
Other guides on this site that pair with this one.
- Buying a home in Carmel
- Buying a home in Carmel-by-the-Sea
- Buying a home in Pebble Beach
- Best real estate agent in Carmel
- Choosing an agent in Carmel-by-the-Sea
- Best real estate agent in Pebble Beach
- Carmel Highlands homes
- Best time to sell in Carmel Highlands
- Point Lobos guide
- Carmel-by-the-Sea building permits
- Building or remodeling in Pebble Beach
Buying or remodeling in the Highlands? Let’s look at the permit picture first.
In Carmel Highlands, what you can build matters as much as what is there today. I help buyers and sellers understand permit history, easements and realistic remodel options before they commit.
Carmel Highlands homesHighlands homes for saleCarmel homes
Questions about Carmel Highlands?
Call or text 831-747-0310, or book a 30-minute call. I am a Broker Associate with Compass, DRE 01980970.
Before you rely on this
- This is a plain-language summary, not legal advice. The County code and the certified Carmel Area plan control, and they can change.
- Whether a specific parcel is appealable, in a scenic road corridor, or subject to earlier conditions is a question for County planning staff.
- Sources checked Nov 17, 2026, except the County permit types page (checked Nov 5, 2026; a Nov 17 fetch timed out).
Carmel Highlands coastal permits: quick questions
Do I need a coastal permit to remodel in Carmel Highlands?
Not always. Maintenance and additions to an existing single-family home are generally exempt under County Code section 20.70.120, unless an exception applies, such as work within 50 feet of a coastal bluff edge, a new well or septic system, or (close to the sea or in a scenic road corridor) an addition of 10% or more of floor area or a new story.
Who issues coastal permits in Carmel Highlands?
Monterey County, under its certified Local Coastal Program (the Carmel Area Land Use Plan is Part 4). Some County decisions can be appealed to the California Coastal Commission.
How long is the Coastal Commission appeal period?
Ten working days after the County’s final action. An appealable permit takes effect only after that period ends or any appeal is resolved.
Can I build on a ridgeline in Carmel Highlands?
The Carmel Area plan says structures should not be sited on non-forested slopes or silhouetted ridgelines in the public viewshed, and that new development in Carmel Highlands must be carefully sited and designed to minimize visibility.
Do I need Design Approval in Carmel Highlands?
Monterey County lists the Carmel Area Land Use Plan among the areas where Design Approval applies, so expect it for new houses and exterior changes.
How long does a Coastal Development Permit last?
For buildings, it stays valid if construction starts within two years, unless the permit says otherwise. The County can extend it by two years on a written request made at least 30 days before expiration.
Get The Balog Report.
Peninsula market notes, Carmel-by-the-Sea and Pebble Beach listings worth a look, and the practical local tips I share with clients between showings.
Want a sample? Read the latest issue. Planning a move? Get in touch.
The next issue of The Balog Report will land in your inbox. Can’t wait? Read the latest issue.